Plan the rollout

Requires @openlatch/client 0.11.12 or later

Plan the waves before the first machine is installed. The wave-1 list, the channel for waves 2 and 3, and the rollback owner are all answers from the prerequisites checklist; this page turns them into a schedule.

Three waves of two weeks each, each one proving something the next depends on. Wave 1 proves the install and the key on real machines. Wave 2 proves your deployment tool. Wave 3 proves the perimeter. Never widen a wave until the one before it meets its exit criteria.

Every wave, the pilot included, enrolls with an organization key, so the people on the machines need no console account. Deploy the client holds the routes.

AttributeWave 1Wave 2Wave 3
ScopeAbout ten machinesAbout fifty machinesThe full perimeter
Install routeOrganization key, by hand on each machine or with a first recipeOrganization key, unattended through your deployment toolOrganization key, unattended through your deployment tool
DurationTwo weeksTwo weeksTwo weeks
ActivityEnroll each machine with the wave’s key, verify it, chase the agents still waiting on the person using them, and write down what people hitPackage the install, prove it on one machine of each operating system, then run it unattended and read the report it collectsRun the same package across the perimeter, and chase the machines that never report
Entry criteriaThe organization is configured, and the wave’s organization key is createdWave 1 met its exit criteria, and the recipe runs cleanly on one machine of each operating systemYour deployment tool is proven on every operating system in the estate, and the proxy scheme is confirmed on every subnet in scope
Exit criteriaEvery enrolled machine reports to the console within 24 hours of install; the client’s own check reports no problem on each; no agent is left waiting on the person using it; the proxy route is confirmed on every operating system in the waveThe same four, plus every machine installed without a developer opening a terminalThe same four, plus the decision to run it as normal operations
Rollbackopenlatch uninstall on the affected machine; the relay CA stays trusted unless you add --purgeThe same, delivered through the tool that installed itThe same, delivered through the tool that installed it
Rollout wavesSix weeks, three waves: what each one proves, and the gate between them.First week: organization, egress, one machine per operating systemWeeks 1 and 2 · Wave 1: organization key, about ten machinesroute provenWeeks 3 and 4 · Wave 2: deployment tool, about fifty machinesexit criteria metWeeks 5 and 6 · Wave 3: full perimeterexit criteria metNormal operationsdecision
Figure 1. Six weeks, three waves: what each one proves, and the gate between them.

Verify each machine and wave is how a machine, and then a wave, is proven against these criteria.

Effort is front-loaded into the first week, when the organization is set up and the route is proven on one machine of each operating system in the fleet. After that, each wave repeats a procedure that already worked.

Phase of workWave 1Wave 2Wave 3Typical effort
Prepare the consoleConnect SAML, set allowed domains and audit retention, invite the rollout team, create the wave-1 organization keyCreate the wave-2 organization keyCreate the wave-3 organization key, and hand over the operating routineA day in the first week, then a few hours a week
Prepare the networkApprove the egress entry and confirm the proxy routeReview the route through your deployment toolNo further changeHalf a day in the first week
Prepare the machinesProve the install on one machine per operating system, then enroll ten machines with the wave’s keyCarry the install in the channel you already operate and run the waveExtend the same channel to the remaining machinesMinutes per machine after the first
Confirm and operateConfirm each installed machine appears in the console’s agent record, with an owner where a directory is connectedWeekly checkpoint and a review of the deployment toolWeekly checkpoint, then the decision to run it as normal operationsA weekly checkpoint through the rollout

Each wave enrolls with its own organization key, created from Host enrollment, so a key that has to be revoked affects one wave only. A machine needs the key only to enroll: it trades it for a host credential of its own, which keeps working after the key is revoked or rotated.

MomentWhat to do with the key
Before the waveAs an admin or owner, create it under Settings › API keys from Host enrollment, name it after the wave, and store it in your secret store. It belongs to the organization, so it keeps working if you leave
During the waveDeliver it to each machine as a key file, through --api-key-file or OPENLATCH_API_KEY_FILE, or as OPENLATCH_API_KEY in the environment the install runs in, never on a command line. openlatch init deletes a key file once the machine is enrolled
Before wave 1, optionalTrust your organization’s relay certificate machine-wide, and check one machine per operating system with openlatch doctor. Every wave then delivers the same bundle beside its own key
After the waveKeep it only for the enrollments still to come. Enrolled machines that run the current client no longer use it; a machine on an earlier client authenticates with it until it updates
To retire itWait for the key’s last-used date to stop moving after the wave’s last enrollment, then delete it, which revokes it. Endpoint management that reruns the install on machines not yet enrolled needs a valid key for as long as it runs

Name the rollback owner before wave 1: the person who can pause a wave and remove the client from a machine. Removal is openlatch uninstall, run on the machine or delivered through the tool that installed it, and it leaves each agent as it was. It keeps the relay CA, still trusted; add --purge to remove it. Uninstall covers removal in full.

  • Three waves of two weeks, all enrolled with an organization key: about ten machines, about fifty through your deployment tool, then the perimeter. Widen only once the previous wave meets its exit criteria.
  • The first week carries most of the effort: the organization, the egress entry, and the install proven on one machine per operating system.
  • One organization key per wave, created from Host enrollment. A machine needs it only to enroll; revoke it once the wave is enrolled on the current client.
  • Name a rollback owner before wave 1. Removal is openlatch uninstall, per machine; the relay CA stays trusted unless you add --purge.